Completed Earthworks Project: 1 Laura Lane, Melrose

Completed Earthworks Project: 1 Laura Lane, Melrose

AsBuilt was contracted to build a platform for a large residential stand in Melrose. Engineers had asked for a 3m excavation in places with the in-situ soild blended with crushed rubble material from the demolition of the pre-existing house. This was done as the soil conditions were’nt conducive to good compaction. We did all the setting out and levelling from a benchmark given to us by the surveyor when we established. We completed the job in 3 weeks, one week ahead of program.

Size: 6000m3 of Cut and 6000m3 of Fill